infrastructure project finance benchmarks

Infrastructure Project Finance Benchmarks: Leverage, Returns, Defaults and Overruns (2026)

Last updated: November 2026

How much debt does an infrastructure project carry, what return does its equity expect, how often does its debt default, and how far do its costs run over? The figures below come from the primary sources: rating agency default studies, government disclosures, the World Bank's Private Participation in Infrastructure database and peer-reviewed research. Each comes with its sample, its period and its scope. Widely repeated figures that could not be traced to an accessible primary source are listed at the end, with the reason each was excluded.


Read this first: what each figure measures

Infrastructure benchmarks are easy to misread because the sources measure different things.

  • Market. The World Bank PPI database covers only low- and middle-income countries. The UK Treasury figures cover UK availability-based PPP contracts. Moody's default study covers project finance bank loans worldwide. A figure from one market does not describe another.
  • Expected or realised. Equity IRRs "at financial close" are what investors expected when the contract was signed. Default rates, recoveries and cost overruns are realised outcomes.
  • Definition of default. Moody's reports project finance defaults under two definitions. The Basel definition is wider: it includes cases where the lender judges the borrower unlikely to pay in full before a payment is missed. Moody's own definition is narrower. The two give different rates on the same loans.
  • Nominal or real. Return figures are given as the source states them. A real IRR and a nominal IRR of the same project can differ by more than two percentage points.

Figures with different scopes are never combined into a single range on this page.


Capital structure and gearing

90% senior debt and 10% equity: the typical funding split of a UK PFI or PF2 project, as described by HM Treasury. "Equity is typically around 10% of the overall financing requirement, with the remaining 90% provided by senior debt (known as the gearing of the project)." HM Treasury notes that equity here includes shares and subordinated debt. Scope: UK Private Finance Initiative and Private Finance 2 contracts, which are mostly availability-based. (HM Treasury, Private Finance Initiative and Private Finance 2 projects: 2018 summary data, May 2019)

68% of private infrastructure investment commitments in low- and middle-income countries were financed by debt in 2024. Down from 75% in 2023, against a five-year average of 66%. Private equity rose from 24% to 30.6% of commitments (five-year average 33%). Within debt, international debt rose to 47% of commitments and local debt fell from 35% to 22%. Scope: projects with private participation at financial close, primary transactions only, excluding refinancings and M&A. (World Bank, Private Participation in Infrastructure 2024 Annual Report)


Cost of capital and equity returns

5% to 6%: cost of capital for a utility-scale solar PV project in advanced economies, against 9% to 12% in emerging and developing economies. From the IEA's survey of financiers and investors, for a 100 MW solar PV project, in nominal, post-tax, local-currency terms; "advanced economies" means the United States and Europe, and values are average medians across countries. For a 40 MW utility-scale battery project, the ranges are 5% to 7% and 9% to 14%. The IEA concludes that the cost of capital for utility-scale solar in emerging and developing economies is "well over twice as high" as in advanced economies. (IEA, Reducing the Cost of Capital, executive summary, 2024)

12% to 15%: the expected equity return when UK PFI contracts were signed, before 2012. As reported by HM Treasury, citing the National Audit Office's 2012 report Equity Investment in Privately Financed Projects. These are expected returns at contract signature, not realised returns. (HM Treasury, May 2019)

11.49% nominal (8.77% real): average expected equity IRR, with fees, of the four PF2 projects still running at 31 March 2018. Ranges: 10.47% to 12.26% nominal, 7.74% to 9.52% real. Across all six PF2 projects, including the Midland Metropolitan Hospital (terminated after Carillion's liquidation, equity written down) and the Midland schools batch (in administrative receivership), the average falls to 7.66% nominal and 5.85% real. The average nominal weighted average cost of capital of the six projects is 4.24% (range 4.04% to 4.64%). (HM Treasury, May 2019)

1.17: public market equivalent of 266 equity investments in core infrastructure in emerging and developing economies, against the S&P 500. Against the MSCI Emerging Markets index, the public market equivalent is 1.26. A ratio above 1 means the investments returned more than the listed index over the same cash flows. Scope: equity investments by the International Finance Corporation (World Bank Group), mostly in unlisted firms, with start dates from 1961 to March 2020. (Chari, Henry, Lee & Mauro, NBER Working Paper 34537, December 2025)


Default and recovery rates

All figures in this section come from Moody's study of project finance bank loans contributed by a consortium of lenders, covering 1 January 1983 to 31 December 2018. The headline sample is the infrastructure, power, and oil and gas sectors: 7,354 projects, which represent 85.7% of the 8,583 loans in the full data set. (Moody's Investors Service, Default and recovery rates for project finance bank loans, 1983-2018: Sustainable project finance bank loans, 17 August 2020)

5.0% (Basel definition) or 3.2% (Moody's definition): 10-year cumulative default rate of project finance bank loans. For the full data set of Moody's March 2020 study, which also includes sectors with historically higher default risk (manufacturing, metals and mining, media and telecom), the 10-year cumulative default rate is 5.5% (Basel) or 3.7% (Moody's).

81.5% (Basel) or 79.5% (Moody's): average ultimate recovery rate on defaulted project finance bank loans. The median ultimate recovery for most subsets is 100%. The full data set of the March 2020 study shows 77.9% (Basel) and 75.8% (Moody's). Recoveries exclude any payment under political risk insurance.

Year 7: by then, marginal default rates of project finance bank loans tend to fall to levels consistent with single-A rated corporate debt. Moody's adds that differences by jurisdiction and use of proceeds "largely diminish by years 5-7 once a project has established an operating track record." Default risk is concentrated in construction and the first years of operation.

4.2%: 10-year cumulative default rate (Basel) of the infrastructure sector in Moody's March 2020 study. Infrastructure projects there are mostly transportation, social and environmental projects. Within the 1983-2018 sample, social projects (hospitals, schools, often paid by availability payments from a public offtaker) show the lowest 10-year rate: 1.1% (Basel) or 0.4% (Moody's). Green projects show 4.9% (Basel) or 2.9% (Moody's), and non-green projects 7.1% (Basel) or 4.7% (Moody's).


Cost overruns and delays

86%: the likelihood that a transport infrastructure project's actual cost exceeds its estimate. From 258 transport projects (bridges, tunnels, highways, freeways, high-speed rail, urban rail and conventional rail) in 20 countries on 5 continents, worth about $90 billion in 1995 prices, comparing actual construction costs with the estimate at the time of the decision to build. The authors find that cost underestimation "has not decreased over the past 70 years." (Flyvbjerg, Skamris Holm & Buhl, "Underestimating Costs in Public Works Projects: Error or Lie?", Journal of the American Planning Association 68(3), 2002)

27.6%: average cost escalation of those 258 projects, in fixed prices. By type: rail 44.7% (58 projects), fixed links such as bridges and tunnels 33.8% (33 projects), roads 20.4% (167 projects). Standard deviations are large (38.7 percentage points across all projects, 62.4 for fixed links), so an average says little about any single project. (Flyvbjerg, Skamris Holm & Buhl, 2002)

51.4%: average demand shortfall of rail projects, on top of their average 44.7% cost overrun. For roads, Flyvbjerg adds that a 20.4% average cost overrun combines with "a fifty-fifty risk that demand is also wrong by more than 20 percent." The same paper states that nine out of ten megaprojects have cost overruns and that overruns have stayed high and constant over the 70-year period for which comparable data exist. (Flyvbjerg, "What You Should Know about Megaprojects and Why: An Overview", Project Management Journal 45(2), 2014)

8.5% of major projects are completed on budget and on time; 0.5% on budget, on time and with the expected benefits. And 47.9% finish on budget. From the database of major projects compiled by Bent Flyvbjerg and presented in How Big Things Get Done (with Dan Gardner, 2023). This database covers major projects of all kinds, not infrastructure only. (Pan Macmillan, publisher's article by the authors)


Investment volumes

All figures in this section come from the World Bank's PPI database, which tracks infrastructure projects with private participation in low- and middle-income countries at financial close, primary transactions only (no refinancings, M&A or secondary trades). The World Bank notes that smaller projects not reported by major media, official databases or governments may be under-represented. (World Bank, Private Participation in Infrastructure 2024 Annual Report)

$100.7 billion: private investment commitments in infrastructure in low- and middle-income countries in 2024. Up 16% from $87.1 billion in 2023 and 20% above the five-year average of $83.7 billion; the first time above $100 billion since the start of the COVID-19 pandemic. The number of projects fell from 324 to 315.

$67.9 billion across 217 projects went to energy in 2024. Transport drew $20.6 billion across 38 projects, "well below historic peaks". ICT reached a record $10.5 billion. Water fell to $1.3 billion and municipal solid waste drew $326 million across nine projects.

$9.2 billion across 18 data centre projects in 2024, a threefold increase on the previous year. Energy storage drew $12 billion across 22 projects, a fivefold increase concentrated mostly in China.


Sources

  • HM Treasury, Private Finance Initiative and Private Finance 2 projects: 2018 summary data, May 2019 (chapter 3, equity return data as at 31 March 2018). Link
  • World Bank, Private Participation in Infrastructure (PPI) 2024 Annual Report (data year 2024). Link
  • International Energy Agency, Reducing the Cost of Capital: Strategies to Unlock Clean Energy Investment in Emerging and Developing Economies, executive summary, 2024. Link
  • Anusha Chari, Peter Blair Henry, Yanru Lee & Paolo Mauro, "Financial Returns to Equity Investments in Infrastructure in Emerging-Market and Developing Economies", NBER Working Paper 34537, December 2025. Link
  • Moody's Investors Service, Default and recovery rates for project finance bank loans, 1983-2018: Sustainable project finance bank loans (addendum to the March 2020 study), 17 August 2020. Link
  • Bent Flyvbjerg, Mette Skamris Holm & Søren Buhl, "Underestimating Costs in Public Works Projects: Error or Lie?", Journal of the American Planning Association 68(3), 2002, 279-295 (author's accepted manuscript on arXiv). Link
  • Bent Flyvbjerg, "What You Should Know about Megaprojects and Why: An Overview", Project Management Journal 45(2), 2014, 6-19 (author's version on arXiv). Link
  • Bent Flyvbjerg & Dan Gardner, How Big Things Get Done, 2023; figures as stated by the authors on the publisher's site. Link

Excluded figures (and why)

  • S&P Global Ratings infrastructure default statistics (an average annual default rate of 0.73% for project finance since 1981, a 0.6% infrastructure default rate in 2023, average project finance loan recoveries of 77% with a median of 92% for 1980-2014). They appear in search summaries of S&P's annual infrastructure default studies, but the S&P pages and PDFs could not be opened during this review. Excluded until checked against the study itself.
  • Moody's project finance default studies after 1983-2018 (editions covering 1983-2021 and, for infrastructure, 1983-2022). Listed by Moody's, but behind a subscription; their figures could not be read. The page uses the latest edition available in full and will move to a newer one once accessible.
  • "Typical gearing of 70% to 80% for renewables" and similar sector bands. Common in lender and adviser material, with no survey, sample or primary publication behind the bands. Excluded. The two measured gearing figures above (UK PFI/PF2, PPI database) are the traceable versions.
  • Debt tenors by sector (for example "18 to 25 years for PPP, 15 to 20 for solar"). No freely accessible primary dataset found; transaction databases such as IJGlobal are subscription-only. Excluded.
  • Indicative DSCR thresholds by rating category. The current global criteria of Moody's, S&P and Fitch could not be opened. A 2012 Fitch training deck (indicative 'BBB' average DSCRs of 1.30x in the rating case for contracted solar and wind) predates later criteria revisions. A 2024 Moody's Local Brazil grid is accessible but rates on a Brazilian national scale, not comparable with global ratings. All excluded.
  • Unlisted infrastructure equity index returns (EDHECinfra infra300 at 8.1% in 2022 and 14.1% in 2023). Found only in an asset manager's market report, not on an EDHECinfra primary page. Excluded pending the primary source.
  • "A database of more than 16,000 projects in 136 countries" for Flyvbjerg's research. Repeated in book reviews, not stated on the publisher's page used here. The page cites the percentages only.
  • "The typical PFI project is financed 90% by debt and 10% by equity", attributed to the National Audit Office's 2018 report. Not verified in the NAO report itself. The same split is shipped above with its primary source, HM Treasury's May 2019 publication.
  • Lazard LCOE financing assumptions (a 60% debt, 40% equity split with stated debt and equity costs). These are modelling assumptions, not measured benchmarks, and the 2025 PDF could not be downloaded during this review. Excluded.

Changelog

  • 2026-11: Initial version. Capital structure (HM Treasury 2019, World Bank PPI 2024), cost of capital and equity returns (IEA 2024, HM Treasury 2019, NBER 2025), default and recovery rates (Moody's 1983-2018), cost overruns (Flyvbjerg et al. 2002, Flyvbjerg 2014, Flyvbjerg and Gardner 2023) and investment volumes (World Bank PPI 2024). Nine widely repeated figures reviewed and excluded.

Further reading


Compiled by Layerz.